Curtiss-Wright and Westinghouse Complete Critical Phase of Testing World's Largest Canned Motor RCP
Tuesday, November 16, 2010
Westinghouse Electric Company LLC, working in conjunction
with EMD, a business unit of Curtiss-Wright Flow Control Company (CWFC), is on
schedule to deliver the world's largest canned motor reactor coolant pumps
(RCPs) for use in the AP1000 nuclear power plant after the initial unit
successfully completed the latest in a series of diagnostic testing.
EMD is completing diagnostic testing to confirm minor design
modifications to the RCP implemented since the start of the first AP1000 RCP
testing. The latest results from the testing indicate that the implemented
design changes (made in the areas of material selection and motor design)
resulting from experience will produce a pump that meets stringent Westinghouse
design requirements. Moreā¦
|
|